Timelines and Phases of a Turnkey Fit-Out

The time required for a fit-out is not measured in days on site, but in the sum of design, procurement, and testing. Here's a realistic timetable to build your project schedule on.

The Six Phases

Every turnkey commission goes through six phases. Skipping one doesn't save time: it merely postpones it to later, when it costs more.

PhaseTypical DurationOutput
Site Survey and Brief2 - 5 daysSurvey, existing systems check, access constraints
Detailed Design1 - 3 weeksLayout, specification, bill of quantities, project schedule
Procurement2 - 8 weeksMaterial and equipment orders, approved samples
Workshop Production1 - 4 weeksPre-assembled and tested bespoke elements
On-site Works1 - 6 weeksDemolitions, systems installation, finishes, furniture installation
Testing and Handover2 - 5 daysChecks, declarations of conformity, as-built drawings, training

What Really Extends Timelines

In our experience, the average delay doesn't originate on-site but earlier: internal client approvals, postponed sample approvals, and special supplies ordered late. Materials such as custom glazing, dedicated light fixtures, and food service equipment can have lead times exceeding eight weeks.

How to Condense the Project Schedule

Weeks can be gained by working in parallel: workshop production while demolitions and chases are carried out on site, long lead time orders placed immediately after detailed design approval, and multiple teams working in shifts when the site allows. This approach enables us to guarantee a contractual handover date even on complex sites: the date is protected by planning, not by last-minute overtime.

Frequently asked questions

How long does a retail fit-out typically take?
For a retail unit of 150-250 m², on-site works generally last three to five weeks, preceded by four to six weeks for design and procurement.
Can you work while the shop remains open?
Yes, through night work or specific time slots and area compartmentalisation: labour costs increase, but the number of closure days is eliminated.