Timeline and Phases of a Turnkey Fit-Out Project

The duration of a fit-out project is not measured in construction days, but in the sum of design, procurement, and commissioning. Here is a realistic timeline to build your project schedule on.

The Six Phases

Every turnkey project goes through six phases. Skipping one doesn't save time; it just pushes it later, when it costs more.

PhaseTypical DurationOutput
Site Survey and Briefing2 - 5 daysSite measurements, existing systems verification, access constraints
Detailed Design1 - 3 weeksLayout, specifications, bill of quantities, project schedule
Procurement2 - 8 weeksMaterial and equipment orders, approved samples
Workshop Production1 - 4 weeksCustom elements pre-assembled and tested
On-Site Construction1 - 6 weeksDemolition, MEP systems, finishes, furniture installation
Commissioning and Handover2 - 5 daysInspections, compliance certifications, as-built drawings, training

What Really Extends Timelines

In our experience, the average delay doesn't originate on site but earlier: internal client approvals, postponed sample approvals, and special supplies ordered late. Materials such as custom glazing, dedicated lighting fixtures, and food service equipment can have lead times exceeding eight weeks.

How to Compress the Project Schedule

Weeks are gained by working in parallel: workshop production while demolition and rough-ins are performed on site; long lead time orders placed immediately after detailed design approval; multiple crews working shifts when the site allows. This approach enables us to guarantee a contractual delivery date even on complex projects: the deadline is secured through planning, not through last-minute overtime.

Frequently asked questions

How long does an average retail fit-out take?
For a 150-250 m² retail space, on-site construction generally lasts three to five weeks, preceded by four to six weeks for design and procurement.
Can you work while the store is open?
Yes, through night work or specific time slots and area compartmentalization: labor costs increase, but the number of closure days is eliminated.